Special box dies for product launches: How should you set up approval and delivery schedules?
When the launch date is set, it is not enough to simply determine a dispatch day for the cutting die. Product dimensions, print design, samples, and final approval must also be scheduled. Delivery expectations turn into a real production plan as these steps become clear.
Plan backwards from the finished packaging
Write down how the packaging, gluing, printing, and cutting stages will proceed in the project. At which stage the cutting die needs to be ready is evaluated according to this plan. It is not assumed that every task will be completed in the same duration.
When necessary files and materials will be ready is also part of the schedule. Preparing a design from an unmeasured visual and releasing an approved drawing to production do not have the same starting point.
Establish a single decision record and a single final version
Sales, marketing, design, and production teams must view the same revision. When product dimensions change, which dieline, print, and sample have been updated is listed. Determining who will give final approval makes it easier to track pending files.
Instead of just writing "updated" in the revision note, specify the changed panel, window, or creasing line. This allows affected production data to be re-checked.
Weigh scope and reuse in limited series
In custom cutting die decisions, production volume, the design's use in other products, and the reorder plan are evaluated together. Cutting die preparation should be read separately from printing and other production costs.
Drawing and sample verification are not skipped even for urgent requests. Share the requested date so that applicable lead times can be clarified further based on production scope and the current plan.
Must be included in the launch brief
- Target date and responsibles for production stages.
- Product, material, and final print/drawing file.
- Sample and approval schedule; decision-maker.
- Quantity, reuse, and revision expectation.
Forward the technical file along with the schedule to Özkardeşler. Let us plan cutting die delivery together without leaving it as a date independent of the other stages of the project.
Frequently asked questions
Does saying urgent definitely mean same-day delivery?
Lead times are verified along with files, technical scope, and production plans.
Is a custom cutting die logical for a limited series?
It is compared based on quantity, design requirements, total production scope, and reuse plans.